GE LM2500 Turbine Compressor Controls Retrofit (Texas, USA)
Tarco Scope:
- Retrofit two Stuart & Stevenson LM2500 packages in Texas
- The replacement of the existing Unit Control System and Compressor Anti-Surge / Load Sharing system with Tarco designed redundant Allen Bradley ControlLogix PLCs
- Design, procure, install and integrate all instrumentation required for the LM2500s
- A brand new control building was built to accommodate new MCCs, UPS, and Control Panels
- Replacement of all existing electrical and controls cabling on site
- Upgrade of the existing Fire and Gas detection system
- Upgrade of the existing Vibration system
- Served as the primary contractor on site. Responsibility included coordinating and directing all engineering and site activities during the project
- Performed detailed planning and pre-work, so that the commissioning window was not exceeded thus ensuring a project success